When one task cannot be done unless another task is done first, set up a
dependency to track the relationship between the two tasks.
- In the CollabNet Sites
view, expand a task and select either of the these nodes:
- Right-click Predecessors to specify tasks that must be completed before this task can be done, and choose Create dependency.
- Select Successors to specify tasks that can be completed only after this task is done, and choose Create dependency.
- In the Create Dependency window, enter the ID or browse to the tasks(s) you're relating.
- Enter a comment that describes the relationship and click OK.
Tip: In the CollabNet Sites
view, you can also create dependencies by dragging a task onto another task.
To delete a dependency, right-click a predecessor or successor task and select
Remove dependency.