Create a task when you identify a unit of work that you want to track to completion
as part of your project.
-
In the CollabNet Sites view, right-click a TeamForge task folder and select .
-
On the New Task page, provide a name for the task.
-
Assign the task a priority between 1 (highest) and 5 (lowest).
-
Assign the task a status.
- Not Started
- OK
- Warning
- Alert
- Complete
-
Give the task a start and end date by making a selection from the
calender.
-
In the Estimated Hours field, write the time you think
is needed to complete the task.
-
Enter a description for the task.
-
Assign the task to an individual, by selecting a project member in the
Assigned To field.
-
Click Submit.