After you configure your Kanban Board, start using it to view, plan and track work
items for the selected planning folder or the selected team within that planning
folder.
-
Click TRACKERS in the project navigation bar.
-
In the List Trackers, Planning Folders and Teams page,
click Kanban.
-
Select the required Kanban Board from Manage
Boards.
The selected Kanban Board for the current project context is
displayed.
-
Select the planning folder for which you want to view the status of the
artifacts.
If your project contains teams, the Select a Team
drop-down list appears. From this drop-down, select All
artifacts or if you want to view artifacts specific to a team
within the selected planning folder, select the relevant team.
Depending upon your selection, artifacts pertaining to the mapped
trackers are displayed in the appropriate swimlane.
- You can view a maximum of 5 swimlanes at a time on your Kanban Board. If
there are more, use the carousel scroll to slide across the swimlanes.
You can expand or collapse each swimlane. When there are no results to
display in a swimlane, the Expand/Collapse button
does not appear.
- Based on the configuration values, if the constraints are violated, the
relevant status headers are highlighted appropriately. A violation of
minimum constraint is highlighted in orange indicating that resources
are underutilized whereas that of maximum constraint is highlighted in
red indicating resources being overloaded and bottlenecks to be fixed.
For more information on how a kanban board is configured, see Set up Kanban Board.
- Each swimlane header displays the status label, the total number of
artifacts within the selected planning folder, and the minimum and
maximum constraints that were configured for the kanban state.
In the above scenario, for the 'In Progress' status:
'3'
is the total number of artifacts in the 'In Progress' status within
the selected planning folder.
'2' indicates the minimum
constraint and '*' indicates the maximum constraint '-1'. (-1 as the
minimum constraint translates to 0 whereas -1 as maximum indicates
there is no limit and so represented by an *.)
Important: These values and constraint validation are planning
folder specific and not team specific. For example, in the above
scenario, the total number of artifacts is the overall count of
artifacts which are in the 'In Progress' status within the selected
planning folder and not within the selected team.
- Each artifact card displays its points (story points) or estimated
effort if these fields are enabled in your tracker settings. If both are
enabled, only the estimated effort is displayed hovering the mouse on
which the artifact's points is displayed. Similarly, if all the effort
fields (estimated, remaining and actuals) are enabled, you can view them
by hovering the mouse on the estimated effort.
- Cards have a color-coded bar to visually identify the priority.
- A parent artifact card displays the count of its child artifacts
(Show/Hide child artifacts button). Click
this button to view or hide the child artifacts. If there are more than
5 child artifacts, when you expand the parent artifact, you will see
pagination arrows ('Previous'/Next') at the bottom of the parent
artifact card.
- If the tracker types of both the parent and child artifacts have been
mapped with the kanban statuses, the child artifacts appear within their
parent artifact card and also as an individual card. In the above
scenario, Epic (parent artifact) and Story (child artifact) trackers
have been mapped to the kanban status 'In Progress'. Story 'artf1014' is
the child artifact of the epic 'artf1002'. So you will see 'artf1014'
within the parent artifact card as well as outside of it as an
individual artifact card.
- When a child artifact is closed, a 'Closed' tag appears next to the
child artifact ID within the parent artifact card.
Edit artifacts
As part of your planning, use Kanban Board to edit
an artifact using the Edit icon on the artifact card or move artifacts from one
status to another appropriately. Based on the status changes you make, the
swimlane headers get updated appropriately.
Remember: The changes you
see in swimlane headers do not apply to any specific team but takes into
account the total count of artifacts within the selected planning
folder.
-
When you drag the artifacts from one swimlane to another, note the following
validations:
- The changes you see in swimlane headers do not apply to any specific
team but takes into account the total count of artifacts within the
selected planning folder.
- You cannot move an artifact card to a status that is not mapped to that
particular tracker type. For example, a 'Ready for QA' kanban status may
not have been mapped to any of the epic tracker statuses. So when you
attempt to move an epic to that status, you will get an Invalid
status configuration error.
- You can move a parent artifact to the 'Closed' status only if all its
child artifacts are closed. However, a child artifact is independent of
its parent with regard to the status change, that is, when you move a
parent artifact from one status to another, the status of the child may
still remain unchanged. For example, an epic may have many stories, the
status of some may change from 'Not Started' to 'In Progress' whereas
some may not. So when the status of an epic as one single unit may
change, it need not apply to all of its child artifacts.
- When your move violates a constraint (minimum or maximum), a warning is
displayed; but you can still move the artifacts.
- If a kanban status is mapped to more than one tracker status, when you
move an artifact, you have an option to choose a status as shown in the
following screen shot.