Task dependencies allow you to establish relationships between tasks. Task
dependencies show what must be done before a given task and what will be done after the task
is complete.
-
Click TASKS in the project navigation bar.
-
On the Task Summary page, find the task folder containing
the task that you want to view.
-
Click the task name.
-
On the
View
Task Details page, click the
DEPENDENCIES
tab.
For each predecessor and successor task, you can see the person to whom the task is
assigned, any issues with the task, the start and end dates, and the effort expended on
the task. For details about a predecessor or successor task, including that task's
predecessors and successors, click the task name.