Make a task depend on another task

When one task cannot be done unless another task is done first, set up a dependency to track the relationship between the two tasks.

  1. In the Site Explorer view, right-click a TeamForge task and select Edit.
  2. In the task editor, click the Dependencies tab. The list of existing dependencies appears.
  3. Add a predecessor or successor task.
    • Drag a task from the Site Explorer tree and drop it in the Predecessors or Successors section.
    • If you know the task ID, enter it in the Predecessors or Successors section and click Add.
    The Predecessor or the Successor section lists the dependency you added. To view the predecessor or successor task, double-click the corresponding entry.
  4. Click Submit to save your changes.