Create a task when you identify a unit of work that you want to track to completion
as part of your project.
-
In the CollabNet Site Browser
view, right-click
a TeamForge task
folder and select Create Task.
-
In the task editor, provide a title and description for the task.
-
Assign the task a priority between 1 (highest) and 5 (lowest).
-
Assign the task to an individual.
Click the Assigned To button to list the
project members to whom you can assign the task.
-
Assign the task a status.
- Not Started
- OK
- Warning
- Alert
- Complete
-
Give the task a start and end date.
Click the calendar icon to select dates.
-
In the Estimated Effort field, write the time you
think is needed to complete the task.
Note: On sites running TeamForge 5.2 or earlier, this field is
called Estimated Hours.
-
Specify whether the time estimate is based on a five-day or seven-day
calendar.
Note: Choose a seven-day calendar to assign a start or end date that
falls on on a weekend.
-
Click Submit to submit your changes to the
server and save your work.